Year Four Project Summary | 2024/25

  • Amount of Funding Awarded - £392,582.94
  • Projects funded - 8
  • Number completed - 8 Projects
  • Projects Number in progress - 0 Projects

Kitchen Extension Ochiltree Hub

Funding was awarded to create a kitchen extension for the hub.

  • Location: Ochiltree
  • PBIP Allocation: £135,552.4
  • Place and Wellbeing Outcome: Resources
  • Organisation status: SCIO
  • Completion status: In Progress

This project was extended into 2025-26 with EAC REF £50,000.

Once tender was issued and returned shortfall of £37,868.88.

Contact Information

Alex Baird | alexbaird9@outlook.com | www.ochiltreehub.com

New Flooring - Yipworld


Funding paid for the removal of old flooring and the installation of new upgraded floors in the centre.

  • Location: Cumnock
  • PBIP Allocation: £3,456
  • Organisation status: Charity
  • Place and Wellbeing Outcome: Resources
  • Completion status: Complete

Contact Information

Janice Hendry, Chief Executive | jhendry@yipworld.org

Path Network Foundations Community Open Garden - Shortlees (COGS)

Funding was awarded for the creation of a path network to complement the existing community garden, by becoming fully accessible and allowing wider access to those within the community.

  • Location: Shortlees, Kilmarnock
  • PBIP Allocation: £20,431
  • Organisation status: SCIO
  • Place and Wellbeing Outcome: Spaces
  • Completion status: Complete

Contact Information

Community Led Regeneration Team | towncentreregeneration@east-ayrshire.gov.uk

Waterlip Path Improvement Project -DART


Funding was awarded to aid the resurfacing and improvement of the waterslip paths along a section of the river to allow inclusive accessibility to all users.

  • Location: Irvine Valley
  • PBIP Allocation: £20,000
  • Organisation status: SCIO
  • Place and Wellbeing Outcome: Spaces
  • Completion status: Complete

Contact Information

George Gardner, Secretary | georgegardner50@googlemail.com | https://discoverdarvel.com

Internal works and refurbishments - The Shed and Nest, Cumnock

Funding was awarded for the continued internal building works and refurbishments of The Shed building.

  • Location: Cumnock
  • PBIP Allocation: £85,000
  • Organisation status: SCIO
  • Place and Wellbeing Outcome: Resources
  • Completion status: Complete

Contact Information

Fraser Stone | Fraser@corra.scot | 07719519373

Mezzanine - Phase 2 - Darvel Community Trust (DART)

Funding was awarded for the second phase of a Mezzanine installation in a gym and sports hall.

  • Location: Darvel
  • PBIP Allocation: £40,000
  • Organisation status: Scottish Charitable Voluntary Organisation
  • Place and Wellbeing Outcome: Resources
  • Completion status: Complete

Contact Information

Community Led Regeneration Team | towncentreregeneration@east-ayrshire.gov.uk

Accessibility ramp - John Knox Church

Funding was awarded for the installation of a ramp to allow accessible access for all to the John Knox Church.

  • Location: Stewarton
  • PBIP Allocation: £35,000
  • Organisation status: Charity
  • Place and Wellbeing Outcome: Resources
  • Completion status: Complete

Contact Information

Graham Whitham, Session Clerk | graham.whitham2@btinternet.com | https://johnknox.org.uk

Central Heating in Netherthird Community Centre (NICE)

Funding was awarded to install central heating to the Netherthird Community Centre and improve energy efficiency of the building.

  • Location: Cumnock
  • PBIP Allocation: £20,076
  • Organisation status: Charity
  • Place and Wellbeing Outcome: Resource
  • Completion status: Complete

Contact Information

Maggie Campbell, Chair | Netherthirdcentre@gmail.com | 01290 428630